题目
项目经理正在为新项目裁剪管理方式:基础设施部分需求明确,面向客户的应用部分不确定性很高。最合适的方式是什么?
A project manager is tailoring the project management approach for a new project. The infrastructure component has well-defined requirements; the customer-facing application has high uncertainty. What is the most appropriate approach?
选项
- A.Use agile for both components to maximise flexibility across the project.
- B.Use agile for infrastructure only since it is the more complex component.
- C.Use predictive for both: consistency across the project simplifies management.
- D.Use predictive for the infrastructure component and agile for the application component: match the methodology to the nature of each deliverable.
解析
解析:D 正确。PMBOK 第 8 版与 2023 版 ECO 明确支持按项目特征裁剪方法。需求明确稳定适合预测型;高不确定、探索性强的工作适合敏捷。采用与各部分性质匹配的混合方式才是正解。强行统一为一种方法论(A 或 C)牺牲效率;给基础设施用敏捷(B)是把敏捷误用于低不确定性工作。
Rationale:D is correct. PMBOK 8 and the ECO 2023 explicitly support tailoring methodology to project characteristics. Well-defined, stable requirements suit predictive delivery; high-uncertainty, exploratory work suits agile. Applying a hybrid approach that matches each component's nature is the correct response. Forcing all components into one methodology (A or C) sacrifices efficiency. Agile for infrastructure (B) misapplies agile to low-uncertainty work.