方法论裁剪 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-305

题目

项目经理正在为新项目裁剪管理方式:基础设施部分需求明确,面向客户的应用部分不确定性很高。最合适的方式是什么?
A project manager is tailoring the project management approach for a new project. The infrastructure component has well-defined requirements; the customer-facing application has high uncertainty. What is the most appropriate approach?

选项

  1. A.Use agile for both components to maximise flexibility across the project.
  2. B.Use agile for infrastructure only since it is the more complex component.
  3. C.Use predictive for both: consistency across the project simplifies management.
  4. D.Use predictive for the infrastructure component and agile for the application component: match the methodology to the nature of each deliverable.
正确答案:D

解析

解析:D 正确。PMBOK 第 8 版与 2023 版 ECO 明确支持按项目特征裁剪方法。需求明确稳定适合预测型;高不确定、探索性强的工作适合敏捷。采用与各部分性质匹配的混合方式才是正解。强行统一为一种方法论(A 或 C)牺牲效率;给基础设施用敏捷(B)是把敏捷误用于低不确定性工作。 Rationale:D is correct. PMBOK 8 and the ECO 2023 explicitly support tailoring methodology to project characteristics. Well-defined, stable requirements suit predictive delivery; high-uncertainty, exploratory work suits agile. Applying a hybrid approach that matches each component's nature is the correct response. Forcing all components into one methodology (A or C) sacrifices efficiency. Agile for infrastructure (B) misapplies agile to low-uncertainty work.

同考点练习题