整合管理 中等 Process 过程域 题号 PMP202611-237

题目

你正在为一个小型、同地办公且经验丰富的敏捷团队裁剪仪式,他们觉得正式的冲刺评审过于繁重。最好的做法是什么?
You are tailoring ceremonies for a small, co-located, experienced agile team. They find formal sprint reviews heavy. What is the BEST approach?

选项

  1. A.Drop the sprint review entirely to save time.
  2. B.Keep the full formal review regardless of team feedback.
  3. C.Tailor the review to a lighter form that still gathers stakeholder feedback.
  4. D.Replace the review with a written status email.
正确答案:C

解析

解析:把评审裁剪得更轻量,既保留其收集反馈的目的,又贴合团队实际。取消评审会失去关键反馈;硬保留重形式则违背裁剪原则;状态邮件是单向的,无法替代互动反馈。 Rationale:Tailoring the review to a lighter format preserves its purpose, gathering feedback, while fitting the team. Dropping it loses essential feedback; keeping a heavy format ignores tailoring; a status email is one-way and cannot replace interactive feedback.