组织 PMO 有标准项目管理方法论。新项目的特征显示敏捷能带来更好结果,但 PMO 强制要求用预测型方法。项目经理应该怎么做?
An organisation's PMO has a standard project management methodology. A new project has characteristics that suggest agile would deliver better outcomes. The PMO mandates predictive methodology. What should the project manager do?
选项
- A.Use agile anyway, the project outcome is more important than PMO compliance.
- B.Follow the PMO mandate without question: methodology compliance is a project manager's obligation.
- C.Use predictive methods publicly while applying agile practices informally within the team.
- D.Present a tailoring proposal to the PMO that explains why agile would better serve the project's characteristics, and request an exception or hybrid approach through proper governance channels.
解析
解析:D 正确。PMBOK 第 8 版明确支持按项目需要裁剪方法论。项目经理有职业责任通过正规渠道为最佳方案发声——正式裁剪提案既尊重治理,又能推动正确方法论落地。无视 PMO(A)违反组织治理;盲从(B)放弃了专业主张的责任;暗中跑敏捷(C)造成信任与透明度问题。
Rationale:D is correct. PMBOK 8 explicitly supports tailoring methodology to project needs. The project manager has a professional responsibility to advocate for the best approach through proper channels, a formal tailoring proposal respects governance while advancing the right methodology. Ignoring the PMO (A) violates organisational governance. Blind compliance (B) ignores the PM's professional responsibility to advocate for the best approach. Secret informal agile (C) creates a trust and transparency problem.