题目
公司的完整方法论要求产出 40 份文档,而你的项目规模小、风险低、周期仅六周。你应该怎么做?
Your company's full methodology requires 40 documents. Your project is small, low-risk and lasts six weeks. What should you do?
选项
- A.Produce all 40 documents.
- B.Tailor the approach to the project's size and risk, agree it with governance and record why.
- C.Skip all documentation.
- D.Refuse the project.
解析
解析:裁剪就是让方法论适配项目实际,同时与治理方确认并记录理由,以保证透明可审计。全做或全不做都是糟糕选择。
Rationale:Tailoring means adapting the method to fit the project, while agreeing and recording the choices keeps it transparent and auditable. Doing everything or nothing are both poor choices.