整合管理 困难 Process 过程域 题号 PMP202611-017

题目

你的新项目包含两部分:第一部分是受监管的诊所建筑,需求固定且明确;第二部分是患者移动应用,功能尚不清晰。你应该建议采用哪种开发方式?
Your new project has two parts. The first is a regulated clinic building with fixed, well-known requirements. The second is a patient mobile app whose features are still unclear. Which development approach should you recommend?

选项

  1. A.Predictive for the whole project.
  2. B.Agile for the whole project.
  3. C.Hybrid: predictive for the building and adaptive for the app.
  4. D.Wait until the app requirements are fully known, then decide.
正确答案:C

解析

解析:考纲要求评估项目需求,推荐预测型、适应型或混合型方式。稳定、固定的工作适合预测型计划;不清晰的工作则受益于短反馈周期。等待只会延误价值交付。 Rationale:The ECO asks you to assess project needs and recommend a predictive, adaptive, or hybrid approach. Stable, fixed work suits a predictive plan. Unclear work gains from short feedback cycles. Waiting delays value.