进度监控与恢复 · PMP 练习题解析

进度管理 困难 Process 过程域 题号 PMP202611-628

题目

你在做一个新 Web 应用项目:与团队重排产品待办优先级、统计以往迭代的速率、据此调整工作计划,并每两周主持一次回顾会。这些工作属于哪个过程?
Leading a new web application project, you reprioritize the product backlog with the team, determine velocity for past iterations, adapt work plans, and facilitate retrospectives every two weeks. Which process describes this work?

选项

  1. A.Monitor Risks
  2. B.Manage Quality
  3. C.Control Schedule
  4. D.Develop Schedule
正确答案:C

解析

解析:在自适应生命周期中,控制进度就体现为:通过回顾会修正过程、重排待办优先级、统计每轮速率并据此调整计划。 Rationale:In adaptive life cycles, Control Schedule includes retrospectives to correct processes, reprioritizing the backlog, determining velocity per iteration and adapting plans.

同考点练习题