整合管理 困难 Process 过程域 题号 PMP202611-319

题目

某组织正在实施企业资源计划(ERP)系统。业务部门向项目经理施压,要求大量定制标准 ERP 以贴合现有流程。最佳建议是什么?
An organisation is implementing an enterprise resource planning (ERP) system. The project manager receives pressure from business units to customise the standard ERP significantly to match existing processes. What is the best recommendation?

选项

  1. A.Delay the ERP implementation until a customisation-friendly version is available.
  2. B.Implement the standard ERP without customisation and ask business units to adapt their processes.
  3. C.Customise the ERP fully to ensure business unit satisfaction and adoption.
  4. D.Evaluate the long-term cost and risk of heavy customisation (upgrade complexity, vendor support, maintenance cost) against the benefits, and present decision-makers with a clear trade-off analysis.
正确答案:D

解析

解析:D 正确。ERP 重度定制是项目失败与上线后成本失控的最常见原因之一。项目经理的职责是让决策者充分理解长期影响,而不是一味满足相关方的短期诉求。清晰的权衡分析才能支撑组织的知情决策。全面定制(C)无视重大风险;完全不定制(B)忽视合理的流程需求;推迟(A)不是解决方案。 Rationale:D is correct. Heavy ERP customisation is one of the most common causes of ERP project failure and post-go-live cost escalation. The project manager's role is to ensure decision-makers understand the full long-term implications, not to simply satisfy short-term stakeholder requests. A clear trade-off analysis empowers an informed organisational decision. Full customisation (C) ignores significant risks. No customisation (B) ignores legitimate process requirements. Delay (A) is not a solution.