项目进度基准原始工期 20 周。因获批的范围增加,基准已更新为 24 周。项目当前预计 26 周。相对当前基准的进度偏差是多少?
A project's schedule baseline shows an original duration of 20 weeks. Due to approved scope additions, the baseline has been updated to 24 weeks. The project is currently tracking at 26 weeks. What is the schedule variance from the CURRENT baseline?
选项
- A.+4 weeks: the schedule expanded from 20 to 24 weeks.
- B.−2 weeks from the current approved baseline of 24 weeks.
- C.−6 weeks from the original baseline.
- D.0 — the baseline was updated so there is no variance.
解析
解析:B 正确。绩效始终对照“当前获批基准”衡量,而非原始基准。当前基准 24 周,预计 26 周,偏差 −2 周(进度落后)。原始基准(C)仅用于历史分析;基准从 20 扩到 24 周(A)是获批范围变更的体现,不是偏差;更新基准并不会消除它与当前预测之间的差距(D)。
Rationale:B is correct. Performance is always measured against the CURRENT approved baseline, not the original. The approved baseline is 24 weeks; the current forecast is 26 weeks, a variance of −2 weeks (behind schedule). The original baseline (C) is relevant for historical analysis but not for current performance measurement. The baseline expansion from 20 to 24 weeks (A) reflects approved scope change. This is not a variance. Updating the baseline doesn't eliminate the gap between it and current forecast (D).