进度监控与恢复 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-458

题目

里程碑最恰当的描述是:
A milestone is best described as:

选项

  1. A.A long task
  2. B.A significant point or event with zero duration
  3. C.A budget approval
  4. D.A team celebration
正确答案:B

解析

解析:里程碑工期为零,用于标记重大事件、跟踪关键成果。 Rationale:Milestones mark significant events with zero duration — used to track major achievements.