题目
你的项目要开发一款医疗设备:硬件按预测型计划推进,软件团队采用两周冲刺。你应如何规划交付?
Your project builds a medical device. The hardware follows a predictive plan, and the software team works in two-week sprints. How should you plan delivery?
选项
- A.Make the software team follow the hardware plan.
- B.Make the hardware team run sprints.
- C.Create an integrated release roadmap that aligns software increments with hardware milestones.
- D.Manage the two teams as separate projects.
解析
解析:混合方法是在合适之处分别采用合适方法,并通过整合计划把两者衔接。把增量与硬件里程碑对齐有利于集成和测试;强行统一方法会丧失混合的优势。
Rationale:A hybrid approach applies each method where it fits and links them through an integrated plan. Aligning increments with hardware milestones supports integration and testing; forcing one method on both loses the hybrid benefit.