某项目关键路径总浮动为 0。一个非关键任务有 5 天浮动,实际延误了 7 天。关键路径会怎样?
A project has a total float of 0 on its critical path. A non-critical task with 5 days of float is delayed by 7 days. What happens to the critical path?
选项
- A.Nothing, the task is non-critical so it cannot affect the critical path.
- B.The task exceeds its float by 2 days, becoming critical and extending the project end date by 2 days.
- C.The task consumes its float but the project end date is unaffected.
- D.The critical path absorbs the delay through management reserve.
解析
解析:B 正确。该任务原有 5 天浮动,延误 7 天会用尽浮动并超出 2 天,这 2 天直接把完工日期推后,该任务因此成为关键路径的一部分(或形成新的关键路径)。浮动只能缓冲到一定限度,超出浮动就直接影响完工日期。非关键任务只要延误超过可用浮动,完全可以影响项目完工(A 错误);管理储备(D)覆盖未知风险,不是进度浮动。
Rationale:B is correct. The task had 5 days of float. A 7-day delay consumes all 5 days and exceeds the float by 2 days. Those 2 excess days push out the project completion date, the task has now become part of the critical path (or created a new one). Float buffers delay to a point, but exceeding the float directly impacts the end date. Non-critical tasks can absolutely affect the project end date if their delays exceed available float (A is wrong). Management reserve (D) covers unknown risks, not schedule float.