题目
某混合项目先有一个固定的合规阶段(预测型),随后是灵活的面向客户的功能交付阶段(敏捷)。合规阶段目前延误 2 周。项目经理应如何应对?
A hybrid project has a fixed regulatory compliance phase (predictive) followed by a flexible customer-facing feature delivery phase (agile). The compliance phase is running 2 weeks late. How should the project manager respond?
选项
- A.Analyse the float available in the compliance phase, identify recovery options (crashing or fast-tracking) and assess the impact on the agile phase start date.
- B.Compress the agile phase by reducing sprint length to recover the 2-week delay.
- C.Accept the delay and inform stakeholders that the project end date will extend by 2 weeks.
- D.Move resources from the agile phase team to the compliance phase to accelerate delivery.
解析
解析:A 正确。正确的第一步永远是先分析选项再行动。合规阶段可能存在可吸收延误的浮动时间,也可能有赶工(加资源)或快速跟进(并行)的空间。只有分析之后才能判断敏捷阶段启动是否真的受影响。压缩敏捷冲刺(B)可能损害质量;直接接受延误(C)跳过分析;抽调敏捷人力(D)在未确认必要时就危及该阶段。
Rationale:A is correct. The correct first step is always to analyse options before taking action. The compliance phase may have float that absorbs the delay; crashing (adding resources) or fast-tracking (parallelising tasks) may be available. Only after analysis can the PM determine whether the agile phase start is genuinely impacted. Compressing agile sprints (B) may harm quality. Immediate acceptance (C) skips analysis. Moving agile resources (D) may jeopardise the agile phase without confirming it is necessary.