在一个混合项目中,预测型部分有一个与监管截止日期绑定的固定里程碑,敏捷部分为其提供输入。你应如何协调?
On a hybrid project, the predictive part has a fixed milestone tied to a regulatory deadline, and the agile part feeds into it. How should you coordinate them?

选项

  1. A.Let the agile part proceed without regard to the milestone.
  2. B.Synchronize the agile increments to deliver what the milestone needs by the deadline.
  3. C.Convert the agile part to predictive to match the milestone.
  4. D.Move the regulatory deadline to fit the agile cadence.
正确答案:B

解析

解析:让增量与固定里程碑同步,既尊重硬性截止日期,又保留敏捷收益,这正是混合协调的核心。无视里程碑可能错过监管时限;改为预测型会丢掉适应性;监管截止日期通常不可由你调整。 Rationale:Synchronising increments to a fixed milestone respects the hard deadline while keeping agile benefits, the essence of hybrid coordination. Ignoring the milestone risks missing a regulatory date; converting to predictive discards adaptiveness; a regulatory deadline is generally not yours to move.