题目
在一个混合项目中,预测型部分有一个与监管截止日期绑定的固定里程碑,敏捷部分为其提供输入。你应如何协调?
On a hybrid project, the predictive part has a fixed milestone tied to a regulatory deadline, and the agile part feeds into it. How should you coordinate them?
选项
- A.Let the agile part proceed without regard to the milestone.
- B.Synchronize the agile increments to deliver what the milestone needs by the deadline.
- C.Convert the agile part to predictive to match the milestone.
- D.Move the regulatory deadline to fit the agile cadence.
解析
解析:让增量与固定里程碑同步,既尊重硬性截止日期,又保留敏捷收益,这正是混合协调的核心。无视里程碑可能错过监管时限;改为预测型会丢掉适应性;监管截止日期通常不可由你调整。
Rationale:Synchronising increments to a fixed milestone respects the hard deadline while keeping agile benefits, the essence of hybrid coordination. Ignoring the milestone risks missing a regulatory date; converting to predictive discards adaptiveness; a regulatory deadline is generally not yours to move.