供方选择与采购流程 · PMP 练习题解析

采购管理 中等 Process 过程域 题号 PMP202611-627

题目

投标人会议上,有供应商指出询价书(RFQ)缺少某一章节,项目经理意识到确实遗漏。收到答复时,除三家外其余供应商都没涉及该章节。最佳做法是:
During a bidder conference, a supplier asks why a section is missing from the RFQ. The PM realizes it is indeed missing. When seller responses arrive, all but three suppliers fail to address the missing section. What is the best course of action?

选项

  1. A.Hold the bidder conference again, and explain the importance of the point that was initially missed
  2. B.Select from the three vendors that submitted complete proposals
  3. C.Send a revised RFQ to all prospective suppliers and allow them the opportunity to resubmit their proposals
  4. D.Extend the deadline and allow all of the vendors to resubmit their proposals
正确答案:C

解析

解析:把更正后的询价书发给所有供应商才公平,也能确保需求被正确理解,还可能带来更多可行报价;只在那三家完整方案里选会扭曲竞争。 Rationale:Re-issuing the corrected RFQ to all suppliers is fair, ensures requirements are understood, and may yield more viable bids; only three complete bids would distort competition.