进度监控与恢复 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-494

题目

进度网络图中的“提前(lead)”指的是:
Lead time in a schedule network diagram refers to:

选项

  1. A.Delay between activities
  2. B.Total project duration
  3. C.Vendor delivery time
  4. D.Overlap allowing a successor to start before the predecessor finishes
正确答案:D

解析

解析:提前即负滞后,是一种重叠,例如编码完成前 2 天就开始测试(FS−2 天)。 Rationale:Lead is negative lag — an overlap, e.g., starting testing 2 days before coding finishes (FS-2 days).

同考点练习题