题目
进度网络图中的“提前(lead)”指的是:
Lead time in a schedule network diagram refers to:
选项
- A.Delay between activities
- B.Total project duration
- C.Vendor delivery time
- D.Overlap allowing a successor to start before the predecessor finishes
解析
解析:提前即负滞后,是一种重叠,例如编码完成前 2 天就开始测试(FS−2 天)。
Rationale:Lead is negative lag — an overlap, e.g., starting testing 2 days before coding finishes (FS-2 days).