进度管理 简单 Process 过程域 题号 PMP202611-103

题目

以下所有因素都会影响活动工期,除了:
All of the following affect the duration of an activity EXCEPT:

选项

  1. A.The anticipated resource needs for the activity
  2. B.The resources allotted to the activity
  3. C.The availability of resources assigned to the activity
  4. D.Scheduling tasks using the precedence diagramming method rather than the critical path method
正确答案:D

解析

解析:工期估算取决于资源类型、数量、技能水平、约束条件与资源日历。选择哪种网络分析技术(PDM 还是 CPM)并不会改变活动本身需要多长时间。 Rationale:Duration estimates depend on resource type, quantity, skill level, constraints, and calendars. The network analysis technique chosen (PDM vs CPM) does not change how long an activity takes.