题目
以下所有因素都会影响活动工期,除了:
All of the following affect the duration of an activity EXCEPT:
选项
- A.The anticipated resource needs for the activity
- B.The resources allotted to the activity
- C.The availability of resources assigned to the activity
- D.Scheduling tasks using the precedence diagramming method rather than the critical path method
解析
解析:工期估算取决于资源类型、数量、技能水平、约束条件与资源日历。选择哪种网络分析技术(PDM 还是 CPM)并不会改变活动本身需要多长时间。
Rationale:Duration estimates depend on resource type, quantity, skill level, constraints, and calendars. The network analysis technique chosen (PDM vs CPM) does not change how long an activity takes.
同考点练习题
-
PMP202611-176 · 答案 C
-
PMP202611-240 · 答案 B
-
PMP202611-261 · 答案 A
-
PMP202611-347 · 答案 B
-
PMP202611-357 · 答案 B
-
PMP202611-458 · 答案 B
-
PMP202611-494 · 答案 D
-
PMP202611-516 · 答案 D