题目
开发人员在租用办公室集中办公。编码耗时超出预期,房东表示办公室已被订满、无法续租。你已把问题记录在项目文件中。下一步应当做什么?
Developers are colocated in rented office space. Coding takes longer than anticipated, and the landlord says the office is already booked for another week. You capture the problem in project documents. What should you do next?
选项
- A.Record the issue in the issue log
- B.Revise the resource management plan
- C.Update the risk register
- D.Deliver the code that has been developed so far
解析
解析:办公场地属于实物资源,实际使用将超出计划。控制资源要求采取纠正措施,更新资源管理计划以反映新的安排。
Rationale:The office is a physical resource; actual utilization will exceed planned. Control Resources requires corrective action, updating the resource management plan to reflect new arrangements.