题目
以下所有内容都应包含在资源管理计划中,除了:
All of the following should be included in a resource management plan EXCEPT:
选项
- A.Responsibilities and roles
- B.Resource identification
- C.Obtaining resources
- D.Project interfaces
解析
解析:资源管理计划说明资源如何被识别、分类、分配、管理与释放,并涵盖角色、职责及项目接口。获取资源是依据该计划执行的后续过程,并不是计划本身的内容。
Rationale:The resource management plan describes how resources will be identified, categorized, allocated, managed, and released, and covers roles, responsibilities, and project interfaces. Acquiring resources is the execution process that follows the plan, not a component of the plan itself.