题目
资源直方图显示某工程师在第 6 周被安排了 70 小时工作,其中部分工作存在浮动时间。你首先应该做什么?
A resource histogram shows one engineer is assigned 70 hours of work in week six. Some of that work has float. What should you do first?
选项
- A.Ask the engineer to work overtime.
- B.Use resource smoothing to move activities within their float.
- C.Delay the whole project.
- D.Remove the engineer from the project.
解析
解析:资源平滑在浮动时间内调整活动,不改变项目完工日期。加班会损害健康与质量;只有在平滑不足时才使用可能改变完工日期的资源平衡。
Rationale:Resource smoothing moves activities within their float so the end date does not change. Overtime harms well-being and quality; resource levelling, which may move the end date, is used only if smoothing is insufficient.