资源管理 中等 People 人域 题号 PMP202611-188

题目

资源直方图显示某工程师在第 6 周被安排了 70 小时工作,其中部分工作存在浮动时间。你首先应该做什么?
A resource histogram shows one engineer is assigned 70 hours of work in week six. Some of that work has float. What should you do first?
资源直方图显示某工程师在第 6 周被安排了 70 小时工作,其中部分工作存在浮动时间。你首先应该做什么?

选项

  1. A.Ask the engineer to work overtime.
  2. B.Use resource smoothing to move activities within their float.
  3. C.Delay the whole project.
  4. D.Remove the engineer from the project.
正确答案:B

解析

解析:资源平滑在浮动时间内调整活动,不改变项目完工日期。加班会损害健康与质量;只有在平滑不足时才使用可能改变完工日期的资源平衡。 Rationale:Resource smoothing moves activities within their float so the end date does not change. Overtime harms well-being and quality; resource levelling, which may move the end date, is used only if smoothing is insufficient.