题目
在最近一次项目状态会上,一名成员反映任务优先级存在冲突。由于存在依赖关系,其他成员的任务现在也被延误。项目经理应如何处理?
At the last project status meeting, a team member reported tasks with conflicting priorities. Other team members are now delayed on their tasks because of dependencies. What should the project manager do to address this situation?
选项
- A.Analyze the critical path and request additional resources
- B.Work with the team members to balance the workload
- C.Create a change request and update the project schedule
- D.Escalate the issue with the team member to their functional manager
解析
解析:当优先级冲突导致依赖延误时,项目经理应先通过资源平衡或平滑,与团队协作重新分配负荷来优化资源。增加资源、变更基准或上报都是在优化无效时才采取的更重手段。
Rationale:When conflicting priorities cause dependency delays, the PM first applies resource optimization—leveling or smoothing—by collaborating with the team to rebalance workload. Extra resources, baseline changes, or escalation are heavier actions reserved for when optimization fails.