资源规划与获取 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-158

题目

两位职能经理都希望在相同几周内使用同一位数据库专家,而你的项目也需要此人。最好的做法是什么?
Two functional managers both want the same database specialist for the same weeks. Your project needs the specialist too. What is the best action?

选项

  1. A.Escalate to the sponsor immediately.
  2. B.Meet both managers to negotiate a plan based on project priorities and timelines.
  3. C.Ask the specialist to choose.
  4. D.Book the specialist first before the others do.
正确答案:B

解析

解析:先与资源所属经理协商才是正确起点,通常能找到各方都能接受的排期。只有在协商失败时才需要上报。 Rationale:Negotiation with the resource owners is the right first step; you can often find a schedule that works for all. Escalate only if negotiation fails.