项目中许多活动争抢同一位专家,造成资源过度分配,而进度允许延长。哪种技术可以解决?
Your project has many activities competing for the same specialist, causing over-allocation. You can extend the schedule. Which technique resolves this?
选项
- A.Crashing.
- B.Resource levelling.
- C.Fast tracking.
- D.Scope reduction.
解析
解析:资源平衡通过调整进度解决过度分配,通常会延长工期,而这在此处可以接受。赶工是加资源压缩工期;快速跟进可能加剧争抢;削减范围是另一类手段。
Rationale:Resource levelling adjusts the schedule to resolve over-allocation, often extending it, which is acceptable here. Crashing adds resources to shorten duration; fast tracking can worsen contention; scope reduction is a different lever.