在弱矩阵组织中,项目经理需要职能部门的专项数据库工程师承担关键路径上一项为期四周的关键任务。职能经理以部门工作优先级更高为由拒绝放人。最合适的做法是?
A project manager in a weak matrix organization needs a specialized database engineer from the functional department for a critical four-week task on the project's critical path. The functional manager refuses to release the resource, citing higher-priority departmental work. What is the most appropriate action?
选项
- A.Escalate directly to the executive sponsor to override the functional manager's decision
- B.Negotiate with the functional manager by offering schedule flexibility or resource sharing, and if unsuccessful, escalate through proper governance channels
- C.Hire an external contractor immediately to fill the resource gap
- D.Adjust the project schedule to wait until the resource becomes available, accepting the delay
解析
解析:在弱矩阵中,职能经理对资源的权限高于项目经理。项目经理应先协商,提出错峰使用、共享资源等创造性方案;协商失败后再走治理渠道上报,而不是直接找高管。
Rationale:In a weak matrix, the functional manager has more authority over resources. The PM should first negotiate—offering creative options such as adjusted timing or shared resourcing—and only then escalate through governance channels rather than jumping to the executive.