资源管理 中等 People 人域 题号 PMP202611-081

题目

以下哪项列出了项目资源管理的主要过程?
Which of the following lists the primary processes of Project Resource Management?

选项

  1. A.Leadership, management, teamwork, and negotiation
  2. B.Create a project staffing plan, recruit a project team, manage personnel actions, and manage labor relations
  3. C.Create an organizational structure, build a project team, create a communication plan, and manage team conflicts
  4. D.Plan Resource Management, Estimate Activity Resources, Acquire Resources, Develop Team, Manage Team, and Control Resources
正确答案:D

解析

解析:项目资源管理由六个过程构成:规划资源管理、估算活动资源、获取资源、建设团队、管理团队、控制资源。其他选项把技能、人事活动或组织设计内容混在一起,并不是标准定义的过程。 Rationale:Project Resource Management comprises six processes: Plan Resource Management, Estimate Activity Resources, Acquire Resources, Develop Team, Manage Team, and Control Resources. The other options mix skills, HR activities, or organizational design elements that are not the defined processes.