题目
一位数据库专家下个月计划投入你的项目 60% 的时间。你了解到她在同一个月还被另一个项目计划投入 60%。你首先应该做什么?
A database specialist is planned at 60% on your project next month. You learn she is also planned at 60% on another project for the same month. What should you do first?
选项
- A.Ask her to work weekends to cover both projects.
- B.Review the resource calendars and work with the other project manager and her functional manager to resolve the conflict.
- C.Escalate the conflict to your sponsor right away.
- D.Remove her from your project and look for someone else.
解析
解析:考纲要求管理并优化资源需求与可用性。上报之前,应先与掌控她时间的人沟通。计划性加班并非可持续的解决方案。
Rationale:The ECO asks you to manage and optimize resource needs and availability. Talk with the people who control her time before you escalate. Planned overtime is not a sustainable solution.