资源规划与获取 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-019

题目

一位数据库专家下个月计划投入你的项目 60% 的时间。你了解到她在同一个月还被另一个项目计划投入 60%。你首先应该做什么?
A database specialist is planned at 60% on your project next month. You learn she is also planned at 60% on another project for the same month. What should you do first?

选项

  1. A.Ask her to work weekends to cover both projects.
  2. B.Review the resource calendars and work with the other project manager and her functional manager to resolve the conflict.
  3. C.Escalate the conflict to your sponsor right away.
  4. D.Remove her from your project and look for someone else.
正确答案:B

解析

解析:考纲要求管理并优化资源需求与可用性。上报之前,应先与掌控她时间的人沟通。计划性加班并非可持续的解决方案。 Rationale:The ECO asks you to manage and optimize resource needs and availability. Talk with the people who control her time before you escalate. Planned overtime is not a sustainable solution.

同考点练习题