某组织重组项目处于执行中,许多关键相关方的岗位职责被打乱,很难维持其积极配合。下列哪项是项目经理最不可能做的?
A corporate restructuring project is in execution. Job responsibilities of many key stakeholders are being disrupted, making it hard to keep them positively engaged. Which action is the PM LEAST likely to perform?

选项

  1. A.Manage stakeholder expectations through negotiation and communication
  2. B.Develop approaches to involve stakeholders based on their needs, expectations, interests, and potential impact on the project
  3. C.Address any risks or potential concerns related to stakeholder management and anticipate future issues
  4. D.Engage stakeholders at appropriate project stages to obtain, confirm, or maintain their continued commitment
正确答案:B

解析

解析:制定参与方式属于“规划相关方参与”,发生在规划阶段,而不是执行阶段的行事。 Rationale:Developing involvement approaches is part of planning the stakeholder engagement plan, which happens during planning — not during execution.