一名成员自愿承担每周向关键相关方做项目状态汇报。第一次会议后,相关方反馈演示效果不佳。项目经理与该成员沟通的最佳方式是:
A team member volunteered to give the weekly project status presentation to key stakeholders. After the first meeting, stakeholder feedback indicates the presentation was not very engaging. What is the best way to address this with the team member?
选项
- A.Discuss the issue with the team member
- B.Prepare a formal written document
- C.Utilize formal verbal communication
- D.Send an email to the team member
解析
解析:沟通媒介应与严重程度和关系匹配。这是志愿者首次出现、并不严重的情况,非正式面谈既设定期望又不至于让人有压力。
Rationale:Choice of media should match severity and relationship. This is a first, non-severe occurrence with a volunteer; an informal face-to-face discussion sets expectations without being threatening.