题目
某大型复杂项目的规划阶段严格遵循了最佳实践。执行中,若干早已识别到的关键风险发生了,项目最终未达成目标。问题可能出在哪里?
During planning of a large complex project, best practices were rigorously followed. During execution, several critical risks that had been foreseen and identified were realized, and the project failed to achieve its objectives. What may have gone wrong?
选项
- A.The realized risks had not been identified earlier in the project
- B.The risk responses were poorly devised
- C.The qualitative risk analysis was inadequate
- D.There was little or no action taken to manage the known risks
解析
解析:典型失败模式:识别、分析、写好了应对,却没人执行。实施风险应对过程就是为了确保约定的应对真的落地。
Rationale:A classic failure mode: teams identify, analyze and document responses, but never execute them. Implement Risk Responses exists to ensure agreed responses are actually carried out.