题目
沟通管理策略通常包含以下所有内容,除了:
A communications management strategy generally includes all of the following EXCEPT:
选项
- A.Communication information, including language, format, topic, and amount of detail
- B.Timetable and frequency for distributing required information and receiving acknowledgement or response
- C.Information delivery methods or technology, such as memos, email, and/or press releases
- D.Project-related email archives, communications, reports, and documentation from all stakeholders
解析
解析:沟通管理计划定义沟通什么、何时、如何、给谁以及由谁沟通。所有相关方的原始邮件存档与文档属于需要管理的项目记录,而不是沟通策略的组成部分。
Rationale:The communications management plan defines what will be communicated, when, how, to whom, and by whom. Raw archives and documents from all stakeholders are project records to be managed, not the strategy itself.