规划沟通管理 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-577

题目

公司中标承建连接两州的跨河大桥,资金来自州政府与联邦政府。项目经理计划用社交媒体与公众沟通。首先应当做什么?
A company is awarded a contract to build a bridge across a river connecting two states, funded by both state and federal governments. The PM plans to use social media to communicate with the public. What should the PM do first?

选项

  1. A.Create a social media policy from scratch
  2. B.Check the resource management plan for social media guidelines
  3. C.Do not use social media because the conversation cannot be controlled and too many people can post negative comments about the project
  4. D.Get the state and federal communication guidelines and reconcile them with the company's social media policy
正确答案:D

解析

解析:使用政府资金就要遵守政府的沟通指引,必须与公司自身的社交媒体政策对照整合,才能确保合规。 Rationale:Government funding brings government communication guidelines; these must be reconciled with the organization's own social media policy to ensure compliance.