规划沟通管理 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-620

题目

你在为施工项目编制沟通管理计划,需要确定相关方的信息需求,重点是所需信息的类型与格式。最佳做法是:
You are developing the communications management plan for a construction project and want to determine the information needs of stakeholders, focusing on the type and format of information required. What is your best course of action?

选项

  1. A.Develop the stakeholder register
  2. B.Review the requirements documentation
  3. C.Conduct a communication requirements analysis
  4. D.Consult the stakeholder engagement plan
正确答案:C

解析

解析:沟通需求分析把信息的类型与格式同信息价值的分析结合起来,从而确定相关方的信息需求。 Rationale:Communication requirements analysis determines stakeholder information needs by combining type and format of information with an analysis of the value of that information.