题目
组织已实践敏捷两年,新任高管以敏捷“不可预测”为由,要求所有项目回到传统瀑布。敏捷实践者最有效的回应是什么?
An organisation has been using agile for 2 years. A new executive joins and mandates a return to traditional waterfall for all projects, citing "unpredictability" of agile. What is the most effective response from the agile practitioners?
选项
- A.Resist the mandate: agile is objectively superior to waterfall.
- B.Seek to understand the executive's specific concerns, present data on agile outcomes achieved, and propose a structured demonstration of agile predictability through proper forecasting tools: addressing the root concern rather than defending methodology.
- C.Continue agile practices informally while nominally following waterfall documentation requirements.
- D.Comply immediately: executive mandates must be followed.
解析
解析:B 正确。“不可预测”是正当的业务关切,值得实质回应,而不是对抗或盲从。弄清具体担心(发布日期?预算?范围?),才能用速率预测、燃起图、发布规划等工具证明敏捷同样能提供可预测性。抵制(A)只有对抗没有建设;立即照办(D)放弃已被验证的做法;暗中跑敏捷(C)不诚实。
Rationale:B is correct. The executive's concern about "unpredictability" is a legitimate business concern that deserves a substantive response, not resistance or compliance. Understanding the specific concern (is it about release dates? budget? scope?) allows practitioners to demonstrate how agile does provide predictability: through velocity-based forecasting, burn-up charts and release planning. Resistance (A) is confrontational without being constructive. Blind compliance (D) abandons proven practices. Secret agile (C) is dishonest.