沟通管理 简单 Process 过程域 题号 PMP202611-561

题目

客户在电话中要求增加一项功能,项目经理口头同意加价 5000 美元并让团队开发。交付后客户验收却拒付这笔费用。这本可以如何避免?
In a phone call, the client requests a feature be added. The PM agrees to include it for an extra $5,000 and instructs the team to develop it. The product is delivered, the client accepts but refuses to pay for the added feature. How could this have been avoided?

选项

  1. A.The project manager could have selected a more appropriate choice of communication media.
  2. B.The scope could have been cut to balance the cost of the feature.
  3. C.The project manager should have requested a lower price for the feature.
  4. D.Nothing could have been done differently.
正确答案:A

解析

解析:沟通媒介的选择是管理沟通的一部分。范围与费用变更应以书面形式确认(例如更新合同),只靠电话口头约定必然留下争议空间。 Rationale:Choice of media is part of Manage Communications. A scope and cost change should have been followed up in writing, e.g. an updated contract, rather than relying on an informal phone agreement.