规划沟通管理 · PMP 练习题解析

沟通管理 困难 Process 过程域 题号 PMP202611-578

题目

为小城供电的新一代核反应堆项目刚启动,公众意见分化:有人担心安全,有人担心超支。项目经理应如何处理潜在风险与问题的对外沟通?
A project to build a new generation nuclear reactor to power a small city has just started. The public is divided: some worry about safety, others about cost overruns. How should the project manager deal with communicating the potential risks and issues?

选项

  1. A.Describe the information sharing process with the public in the communications management plan
  2. B.Risks and issues are internal to the project and do not need to be communicated outside the project.
  3. C.Invite the public representatives to the daily standup meetings with the project team
  4. D.Make the risk register and issue log a public document for the sake of transparency
正确答案:A

解析

解析:沟通管理计划规定沟通如何规划、组织、实施并监控效果,也包括风险与问题如何对包括公众在内的外部相关方共享。 Rationale:The communications management plan describes how communications will be planned, structured, implemented and monitored, including how risks and issues are shared externally with stakeholders such as the general public.