题目
为小城供电的新一代核反应堆项目刚启动,公众意见分化:有人担心安全,有人担心超支。项目经理应如何处理潜在风险与问题的对外沟通?
A project to build a new generation nuclear reactor to power a small city has just started. The public is divided: some worry about safety, others about cost overruns. How should the project manager deal with communicating the potential risks and issues?
选项
- A.Describe the information sharing process with the public in the communications management plan
- B.Risks and issues are internal to the project and do not need to be communicated outside the project.
- C.Invite the public representatives to the daily standup meetings with the project team
- D.Make the risk register and issue log a public document for the sake of transparency
解析
解析:沟通管理计划规定沟通如何规划、组织、实施并监控效果,也包括风险与问题如何对包括公众在内的外部相关方共享。
Rationale:The communications management plan describes how communications will be planned, structured, implemented and monitored, including how risks and issues are shared externally with stakeholders such as the general public.
同考点练习题
-
PMP202611-090 · 答案 D
-
PMP202611-104 · 答案 A
-
PMP202611-314 · 答案 A
-
PMP202611-410 · 答案 B
-
PMP202611-561 · 答案 A
-
PMP202611-577 · 答案 D
-
PMP202611-620 · 答案 C
-
PMP202611-624 · 答案 A