沟通管理 中等 Process 过程域 题号 PMP202611-314

题目

项目经理正在编制沟通管理计划。一位高管相关方偏好简短的口头汇报,而技术团队偏好详细的书面报告。沟通计划应如何处理?
A project manager is creating a communications management plan. A senior executive stakeholder prefers brief verbal updates while a technical team prefers detailed written reports. What should the communication plan do?

选项

  1. A.Tailor communication format, frequency and level of detail to each stakeholder group's stated preferences and information needs.
  2. B.Ask stakeholders to adapt to a single standard format to reduce the PM's workload.
  3. C.Use the executive's preferred format for all stakeholders to keep senior management satisfied.
  4. D.Standardise all communications to one format for consistency and efficiency.
正确答案:A

解析

解析:A 正确。有效沟通要求让信息匹配受众。沟通管理计划应明确记录各相关方群体的沟通需求:形式、频率、详略程度与渠道。“一刀切”(D)在多元受众下必然失效;只顾高层(C)会疏远技术团队;让相关方迁就(B)降低参与度,也违背相关方管理的目的。 Rationale:A is correct. Effective communication requires matching the message to the audience. The communications management plan should explicitly document each stakeholder group's communication needs: format, frequency, detail level and channel. A one-size-fits-all approach (D) inevitably fails for diverse audiences. Prioritising executives only (C) alienates the technical team. Forcing stakeholders to adapt (B) reduces engagement and misses the purpose of stakeholder management.