规划沟通管理 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-104

题目

以下哪项是规划沟通管理过程的输入?
Which of the following are inputs to the Plan Communications Management process?

选项

  1. A.Project management plan, project documents, enterprise environmental factors, and organizational process assets
  2. B.Stakeholder requirements, project scope statement, budget, and timeline
  3. C.Organizational structure, stakeholder analysis, and communication obstacles
  4. D.Stakeholder management approach, RAM, work breakdown structure, and administrative processes
正确答案:A

解析

解析:规划沟通管理的输入包括项目章程、项目管理计划、项目文件(如相关方登记册、需求文件)、事业环境因素与组织过程资产。 Rationale:Plan Communications Management takes the project charter, project management plan, project documents (such as the stakeholder register and requirements documentation), enterprise environmental factors, and organizational process assets as inputs.