题目
以下哪项是规划沟通管理过程的输入?
Which of the following are inputs to the Plan Communications Management process?
选项
- A.Project management plan, project documents, enterprise environmental factors, and organizational process assets
- B.Stakeholder requirements, project scope statement, budget, and timeline
- C.Organizational structure, stakeholder analysis, and communication obstacles
- D.Stakeholder management approach, RAM, work breakdown structure, and administrative processes
解析
解析:规划沟通管理的输入包括项目章程、项目管理计划、项目文件(如相关方登记册、需求文件)、事业环境因素与组织过程资产。
Rationale:Plan Communications Management takes the project charter, project management plan, project documents (such as the stakeholder register and requirements documentation), enterprise environmental factors, and organizational process assets as inputs.
同考点练习题
-
PMP202611-090 · 答案 D
-
PMP202611-314 · 答案 A
-
PMP202611-410 · 答案 B
-
PMP202611-561 · 答案 A
-
PMP202611-577 · 答案 D
-
PMP202611-578 · 答案 A
-
PMP202611-620 · 答案 C
-
PMP202611-624 · 答案 A