质量统计工具应用 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-622

题目

某降低制造缺陷率的项目正在推进,团队正在开展质量保证活动。下列哪项最有帮助?
A project to reduce the manufacturing process defect rate is underway, and the team is carrying out quality assurance activities. Which of the following would be most beneficial?

选项

  1. A.Introducing the use of a kanban board into the manufacturing process
  2. B.Consulting with a certified Six Sigma Black Belt expert
  3. C.Utilizing rolling wave planning for the project
  4. D.Adopting a just-in-time (JIT) manufacturing process
正确答案:B

解析

解析:PDCA 与六西格玛是最常用的质量改进方法;六西格玛黑带正是受训以这些工具做流程改进的人。 Rationale:PDCA and Six Sigma are the most common quality improvement approaches; a Six Sigma Black Belt is trained to apply these tools to process improvement.