项目经理正在获取团队成员,想了解他们的可用性。应如何获取这一信息?
A PM is obtaining team members and wants to understand their availability for project work. What should she do to find this information?
选项
- A.Look at the resource calendars
- B.Contact the project management office
- C.Review the resource requirements
- D.Examine the resource breakdown structure
解析
解析:资源日历标明每个资源何时可用——工作日、班次、工时、周末与假日,是获取资源的输入。
Rationale:The resource calendar identifies working days, shifts, business hours, weekends and holidays when each resource is available — an input to Acquire Resources.