题目
在团队章程会议上,一名成员说:“我不明白这会有多重要,我们都是专业人士,也合作过,不如早点开工。”其他人似乎也认同。你应当如何回应?
While facilitating a team charter meeting, a member says: "I don't understand the importance of this meeting. We are all professionals and have worked together before. Wouldn't our time be better spent starting execution?" Others seem to agree. How should you respond?
选项
- A.As long as everyone is in agreement, then let's skip the team charter and get ahead of schedule
- B.Let's use the team charter from our last project as a starting point and then update it as necessary
- C.The team charter is required by the project management office (PMO) for all projects
- D.The team charter will eliminate any potential conflicts which will improve our productivity
解析
解析:对行为准则的明确共识能减少误解。团队既然合作过,以往有效的章程可作为起点,但仍需一起评审并重新承诺。
Rationale:Explicit agreement on acceptable behavior reduces misunderstandings. Since the team has worked together, a prior effective charter is a good starting point — but it must still be reviewed and committed to.