你正在为项目建立知识管理系统。下列哪项做法最没有帮助?
You are establishing a knowledge management system for your project. Which of the following actions will be the LEAST beneficial?
选项
- A.Reviewing the lessons learned register
- B.Monitoring stakeholder engagement
- C.Examining the resource breakdown structure
- D.Studying the project team assignments
解析
解析:知识管理需要能识别“谁具备什么能力”的文件;监督相关方参与属于关系策略,与知识捕获关系最远。
Rationale:Knowledge management needs documents identifying people and their capabilities; monitoring stakeholder engagement concerns relationship strategy, not knowledge capture.