题目
你负责一个相关方众多的大项目,希望两名新成员尽快了解项目全貌并有效对接相关方。应当怎么做?
You lead a large project with many stakeholders and want two new team members to get up to speed with the project's dynamics and engage effectively. What should you do?
选项
- A.Ask the team members to record any issues they encounter into the issue log
- B.Review the stakeholder register with the new team members
- C.Schedule a meeting with the new team members and all project stakeholders
- D.Submit a change request to update the stakeholder engagement plan
解析
解析:相关方登记册记录每位相关方的身份、评估与分类信息,正是新人快速建立全局认知所需的材料。
Rationale:The stakeholder register holds identification, assessment and classification information about each stakeholder — exactly what newcomers need for context.
同考点练习题
-
PMP202611-029 · 答案 C
-
PMP202611-037 · 答案 C
-
PMP202611-136 · 答案 A
-
PMP202611-149 · 答案 B
-
PMP202611-160 · 答案 B
-
PMP202611-161 · 答案 B
-
PMP202611-222 · 答案 B
-
PMP202611-251 · 答案 B