团队建设与团队章程 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-617

题目

你负责一个相关方众多的大项目,希望两名新成员尽快了解项目全貌并有效对接相关方。应当怎么做?
You lead a large project with many stakeholders and want two new team members to get up to speed with the project's dynamics and engage effectively. What should you do?

选项

  1. A.Ask the team members to record any issues they encounter into the issue log
  2. B.Review the stakeholder register with the new team members
  3. C.Schedule a meeting with the new team members and all project stakeholders
  4. D.Submit a change request to update the stakeholder engagement plan
正确答案:B

解析

解析:相关方登记册记录每位相关方的身份、评估与分类信息,正是新人快速建立全局认知所需的材料。 Rationale:The stakeholder register holds identification, assessment and classification information about each stakeholder — exactly what newcomers need for context.