项目治理与PMO · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-615

题目

多阶段项目到达阶段关口,相关方要判断该阶段是否达到成功标准以及是否继续。除项目管理计划外,还需要哪些文件?
A multi-phase project has reached a phase gate. Stakeholders want to determine if the phase met its success criteria and whether to proceed. In addition to the project management plan, which documents are required?

选项

  1. A.Risk register and risk report
  2. B.Lessons learned register and lessons learned repository
  3. C.Business documents and project charter
  4. D.Agreements including procurement contracts
正确答案:C

解析

解析:阶段关口要审项目章程(成功标准)、商业论证(业务需求与成本效益)与效益管理计划,后两者合称商业文件。 Rationale:A phase gate reviews the project charter (success criteria), business case (need and cost-benefit) and benefits management plan (the last two being business documents).

同考点练习题