题目
多阶段项目到达阶段关口,相关方要判断该阶段是否达到成功标准以及是否继续。除项目管理计划外,还需要哪些文件?
A multi-phase project has reached a phase gate. Stakeholders want to determine if the phase met its success criteria and whether to proceed. In addition to the project management plan, which documents are required?
选项
- A.Risk register and risk report
- B.Lessons learned register and lessons learned repository
- C.Business documents and project charter
- D.Agreements including procurement contracts
解析
解析:阶段关口要审项目章程(成功标准)、商业论证(业务需求与成本效益)与效益管理计划,后两者合称商业文件。
Rationale:A phase gate reviews the project charter (success criteria), business case (need and cost-benefit) and benefits management plan (the last two being business documents).