题目
项目退出标准的主要目的是什么?
What is the main purpose of project exit criteria?
选项
- A.Define vendor termination conditions
- B.Define conditions required to close a phase or the entire project
- C.Identify reasons for the project manager's resignation
- D.Calculate the final budget variance
解析
解析:退出标准规定在正式关闭项目阶段或整个项目之前必须满足的条件。
Rationale:Exit criteria specify the conditions that must be met before a project phase or the entire project can be formally closed.
同考点练习题
-
PMP202611-096 · 答案 A
-
PMP202611-109 · 答案 C
-
PMP202611-127 · 答案 B
-
PMP202611-187 · 答案 B
-
PMP202611-197 · 答案 B
-
PMP202611-363 · 答案 B
-
PMP202611-365 · 答案 B
-
PMP202611-390 · 答案 C