整合管理 中等 Process 过程域 题号 PMP202611-080

题目

项目退出标准的主要目的是什么?
What is the main purpose of project exit criteria?

选项

  1. A.Define vendor termination conditions
  2. B.Define conditions required to close a phase or the entire project
  3. C.Identify reasons for the project manager's resignation
  4. D.Calculate the final budget variance
正确答案:B

解析

解析:退出标准规定在正式关闭项目阶段或整个项目之前必须满足的条件。 Rationale:Exit criteria specify the conditions that must be met before a project phase or the entire project can be formally closed.