在季度项目组合评审中,高管层把组织战略方向转向数字化转型。项目经理手上两个在跑的项目已不再符合新战略。项目经理应该怎么做?
During a quarterly portfolio review, executive leadership shifts the organization's strategic direction toward digital transformation. Two of the project manager's active projects no longer align with the new strategy. What should the project manager do?

选项

  1. A.Continue both projects since they were already approved and funded
  2. B.Present a business case analysis to the portfolio governance board showing the misalignment and recommending options for each project
  3. C.Immediately stop work on both projects to conserve resources for strategic initiatives
  4. D.Modify the project objectives to align with the new strategy without seeking formal approval
正确答案:B

解析

解析:战略对齐是持续过程。战略变化时,项目经理应向项目组合治理机构提交有依据的分析,列出继续、调整或终止等选项。是否继续应由治理委员会而非项目经理依据战略契合度与资源分配来决定。 Rationale:Strategic alignment is continuous. When strategy changes, the project manager presents an informed analysis to the portfolio governance body with options such as continuation, modification, or termination. The governance board—not the PM—decides on continuation based on strategic fit and resource allocation.