题目
项目完工前几周,客户要求加建一个户外桑拿房。分析显示实施较容易且不影响完工日期。首先应当做什么?
A few weeks before completion, the client asks to add an outdoor sauna. Analysis shows it would be fairly easy to implement without impacting the completion date. What should you do first?
选项
- A.Begin construction since the project completion date is not violated
- B.Review the requested change against all other project constraints
- C.Have the sponsor verify if the change violates construction regulations
- D.Consult with the change control board on how to handle the change
解析
解析:即使看似容易,整体变更控制仍要求先评估对范围、成本、质量、风险、资源等各方面的影响再决策。
Rationale:Even with an apparently easy change, integrated change control requires examining impact on scope, cost, quality, risk, resources and other constraints before deciding.