项目治理与PMO · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-187

题目

在看板上,大量条目积压在“测试”列,而开发人员仍在不断开始新条目。最好的做法是什么?
On your Kanban board, many items are waiting in the "Testing" column while developers keep starting new items. What is the best action?

选项

  1. A.Hire more developers.
  2. B.Set work-in-progress limits and ask the team to help clear the testing queue.
  3. C.Skip testing for low-risk items.
  4. D.Add a new column called "Waiting".
正确答案:B

解析

解析:在制品限额能阻止团队开工量超过完成量,并集中力量清除瓶颈以改善流动。跳过测试会损害质量,只是把队列藏起来。 Rationale:WIP limits stop the team from starting more than it can finish, and swarm on the bottleneck to improve flow. Skipping testing harms quality and merely hides the queue.