整合管理 困难 Process 过程域 题号 PMP202611-197

题目

内部安全审计发现部分团队成员拥有其并不需要的生产系统访问权限。你应该怎么做?
An internal security audit finds that some team members have access to production systems they do not need. What should you do?

选项

  1. A.Ignore it until the project ends.
  2. B.Treat it as a compliance issue, plan the fix quickly and report progress through governance.
  3. C.Remove access for the whole team.
  4. D.Ask the auditors to change the finding.
正确答案:B

解析

解析:信息安全属于 2026 考纲的合规范畴。迅速制定修复计划并经治理汇报,能保护组织;取消全员权限则会不必要地中断工作。 Rationale:Security is a compliance area in the 2026 outline. A prompt, planned fix reported through governance protects the organisation; removing all access would needlessly stop the work.