题目
某项目属于一个项目群。项目群经理告知项目经理:项目群内另一项目被取消,释放出大量共享资源。项目经理应该怎么做?
A project is part of a programme. The programme manager informs the project manager that another project in the programme has been cancelled, freeing up significant shared resources. What should the project manager do?
选项
- A.Immediately request the freed resources to accelerate the project schedule.
- B.Assess whether the freed resources could address current constraints, risks or opportunities in the project, then work with the programme manager through proper resource allocation channels to request what is justified.
- C.Do nothing: resource allocation is the programme manager's responsibility.
- D.Request all available resources regardless of need to maximise the project's capacity.
解析
解析:B 正确。项目经理应主动:先分析释放的资源是否真能帮到本项目,再通过正规渠道提出有理有据的申请。不问需求全要(D)既浪费也对项目群其他项目不公;完全不管(C)错失机会;未经分析立即索要(A)属被动反应,也难站得住脚。
Rationale:B is correct. The project manager should be proactive: analyse whether freed resources could genuinely benefit the project, then make a justified request through proper channels. Taking resources without need (D) is wasteful and unfair to other programme projects. Doing nothing (C) misses a potential opportunity. Immediately requesting without analysis (A) is reactive and may not be justified.
同考点练习题
-
PMP202611-080 · 答案 B
-
PMP202611-096 · 答案 A
-
PMP202611-109 · 答案 C
-
PMP202611-127 · 答案 B
-
PMP202611-187 · 答案 B
-
PMP202611-197 · 答案 B
-
PMP202611-365 · 答案 B
-
PMP202611-390 · 答案 C