项目治理与PMO · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-365

题目

项目与项目群的主要区别是什么?
What is the primary difference between a project and a programme?

选项

  1. A.A programme is managed by a senior project manager; projects are managed by junior PMs.
  2. B.A programme is a group of related projects managed in a coordinated way to obtain benefits not available from managing them individually. It focuses on benefits realisation across interrelated initiatives.
  3. C.A programme has a defined end date; projects are ongoing.
  4. D.A programme is a larger project. It simply has more tasks and team members.
正确答案:B

解析

解析:B 正确。PMI 将项目群定义为一组相互关联的项目、子项目群与项目群活动,通过协调管理以获得单独管理所无法实现的收益。关键区别在于为集体收益而协调管理,而非规模更大(D)。项目与项目群都有明确结束日期(C 说反了)。项目群管理是一种专业分工,不是职级(A)。 Rationale:B is correct. PMI defines a programme as a group of related projects, subsidiary programmes and programme activities managed in a coordinated way to obtain benefits not available from managing them individually. The key distinction is the coordinated management for collective benefits, not just scale (D). Both projects and programmes have defined end dates (C is reversed). Programme management is a specialisation, not a seniority level (A).