题目
组织中的项目管理办公室(PMO)类型包括以下各类,除了:
The types of project management office structures in organizations include all of the following EXCEPT:
选项
- A.Supportive PMOs that provide a consultative role by supplying templates, best practices, training, information access, and lessons learned
- B.Controlling PMOs that provide support and require compliance through various means
- C.Harmonizing PMOs that strive to reduce conflict and improve harmony among project team members
- D.Directive PMOs that take control of projects by directly managing them
解析
解析:公认的 PMO 类型只有支持型、控制型和指令型,按控制程度区分。“协调型 PMO”并不存在。
Rationale:The recognized PMO types are supportive, controlling, and directive, distinguished by their degree of control. 'Harmonizing PMO' is not one of them.